| Project Name: | Lower Muscatine Road Reconstruction (Kirkwood Ave. to 1st Ave.) |
| Project's Description: | Reconstruction of Lower Muscatine Road from Kirkwood Avenue to 1st Avenue. Improvements include new roadway, sidewalk, roadway lighting, storm sewer, sanitary sewer, water main, and other associated improvements. |
| Bid Letting Date/Time: | 4/17/2012 10:00 AM |
| Project Schedule Information: | Late Start Date: May 21, 2012
Working Days: 200 Intermediate Completion Dates: Site 1: August 15, 2012 Site 2: 105 Working Days Liquidated Damages: $1,500 per day |
| Engineer's Estimate: | $5,649,000.00 |
| Plans & Specifications Available: | This is an IDOT project [STP-U-3715(637)--70-52].
Contact: Iowa Department of Transportation Office of Contracts 800 Lincoln Way Ames, IA 50010 515-239-1414 www.ia.bidx.com |
| Pre-Bid Conference: | None |
| Contact Person: | Jason Havel, (319) 356-5410 |